Time schedule
    


TIME SCHEDULE
MAIN MILESTONES ACCORDING TO THE GANTT CALENDAR

ACTIVITY DATE
PROJECT INITIATION 01/11/99
SUBSIDY APPLICATION FORM 02/11/99 - 29/11/99
DRAWING UP OF CITY COUNCIL PROJECTS 09/11/99 - 20/12/99
PROJECT PRESENTATION AND APPLICATION FOR EXECUTION LICENCE 20/12/99
DRAWING UP OF INDUSTRIAL TECHNICAL SERVICES 04/01/00 - 27/03/00
INITIATION OF EXECUTION 10/01/00
INDUSTRIAL EXECUTION, SOIL MOV. AND CONSTRUCTION 11/01/00 - 07/08/00
OFFICE CONSTRUCTION 11/04/00 - 04/09/00
INDUSTRIAL FACILITIES EXECUTION 11/07/00 - 28/08/00
OFFICE INSTALLATION EXECUTION 11/07/00 - 07/08/00
PLOT URBANIZATION 11/07/00 - 04/09/00
INITIATION OF MACHINERY ASSEMBLY PROCESS 11/07/00
MACHINERY ASSEMBLY PROCESS ENDS 11/07/00
FINALIZING EXECUTION 04/09/00
INITIATION OF START-UP 05/09/00
START-UP ENDS 02/10/00